[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1265842,853,1,"单选题","实施进度计划的核心是进度计划的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检查措施落实情况",false,{"key":16,"text":17,"correct":18},"B","动态跟踪控制",true,{"key":20,"text":21,"correct":14},"C","分析计划执行情况",{"key":23,"text":24,"correct":14},"D","跟踪检查，收集实际数据","实施进度计划的核心是进度计划的动态跟踪控制。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]