[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265841":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1265841,853,1,"单选题","项目目标动态控制的核心是在项目实施的过程中定期进行（ ）的比较，当发现项目目标偏离时应采取纠偏措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目目标的计划值和偏差值",false,{"key":16,"text":17,"correct":14},"B","项目目标的实际值和偏差值",{"key":19,"text":20,"correct":21},"C","项目目标的计划值和实际值",true,{"key":23,"text":24,"correct":14},"D","项目目标的现期值和初期值","在项目实施过程中（如设计过程中、招投标过程中和施工过程中等）对项目目标进行动态跟踪和控制：收集项目目标的实际值，如实际投资成本、实际施工进度和施工的质量状况等；定期（如每两周或每月）进行项目目标的计划值和实际值的比较；通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]