[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265825":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1265825,853,1,"单选题","关于设计变更的注意事项，下列说法中正确的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计变更必须要说明变更原因，其产生的背景可根据情况附加",false,{"key":16,"text":17,"correct":14},"B","建设单位对设计图纸的合理修改意见，一般在施工过程中提出",{"key":19,"text":20,"correct":14},"C","工程造价增减幅度必须在总概算范围之内",{"key":22,"text":23,"correct":24},"D","在施工试车过程中，只要不影响生产，一般不再接受变更要求",true,"设计变更必须说明变更原因和产生的背景。如工艺改变、工艺要求、设备选型不当，设计者考虑需提高或降低标准、设计漏项、设计失误或其他原因；变更产生的提出单位、主要参与人员、时间等的背景。故选项A错误。建设单位对设计图纸的合理修改意见，应在施工之前提出。故选项B错误。工程造价增减幅度控制在总概算慎重。故选项C错误。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]