[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265820":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1265820,853,1,"单选题","消防水泵及稳压泵的施工程序中，泵体安装的紧后工序是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","泵体稳固",false,{"key":16,"text":17,"correct":18},"B","吸水管路安装",true,{"key":20,"text":21,"correct":14},"C","压水管路安装",{"key":23,"text":24,"correct":14},"D","单机调试","防水泵及稳压泵的施工程序为：施工准备一基础施工一泵体安装一吸水管路安装一压水管路安装一单机调试。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]