[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265812":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1265812,853,1,"单选题","项目部对反应塔基础的坐标位置及标高，预埋地脚螺栓的坐标位置及标高应进行（ ），其允许偏差应符合设计文件或国家现行有关规范的规定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检查",false,{"key":16,"text":17,"correct":18},"B","复测",true,{"key":20,"text":21,"correct":14},"C","查看记录",{"key":23,"text":24,"correct":14},"D","交接验收","反应塔预埋地脚螺栓的直径很大，数量很多，一旦预埋的位置不准或者是标高不对，会给设备就位造成很大的麻烦。所以一定要割。“检查”不明确，“查看记录”与“交接验收”没有“复测”的含义，所以A、C、D不是正确选项。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]