[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1265765,853,1,"单选题","按照建筑给水、排水、供热及采暖管道工程的一般施工程序，在完成管道安装之后，下一步应进行的施工程序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管道附件检验",false,{"key":16,"text":17,"correct":14},"B","管道防腐绝热",{"key":19,"text":20,"correct":14},"C","管道系统清洗",{"key":22,"text":23,"correct":24},"D","管道系统试验",true,"建筑设备管道系统中的给水、排水、供热及采暖管道工程的一般施工程序是：施工准备一配合土建预留、预埋一管道支架制作一附件检验一管道安装一管道系统试验一防腐绝热一系统清洗一竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]