[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1265729,853,1,"单选题","钢结构一般安装顺序应为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","构件检查一支撑安装一维护结构安装一钢柱安装",false,{"key":16,"text":17,"correct":14},"B","钢柱安装一构件检查一支撑安装一维护结构安装",{"key":19,"text":20,"correct":21},"C","构件检查一钢柱安装一支撑安装一维护结构安装",true,{"key":23,"text":24,"correct":14},"D","钢柱安装一维护结构安装一支撑安装一构件检查","钢结构一般安装顺序是：构件检查一基础复查一钢柱安装一支撑安装一梁安装一平台板c层板、屋面板）安装一维护结柄安装。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]