[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1265634,853,1,"单选题","高程控制测量时，两次观测超差较大时应重测。将重测结果与原测结果分别比较，其差均不超过限值时，可取（ ）次结果的平均数。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","五",false,{"key":16,"text":17,"correct":14},"B","四",{"key":19,"text":20,"correct":21},"C","三",true,{"key":23,"text":24,"correct":14},"D","两","高程控制测量时，两次观测超差较大时应重测。将重测结果与原测结果分别比较，其差均不超过限值时，可取三次结果的平均数",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]