[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1265591,853,1,"单选题","设备的抄平主要通过平尺和水平仪按照施工规范和设备技术文件要求偏差进行，以下说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在较大的测定面上测量水平度时，应放上平尺，再用水平仪检测，两者接触应",true,{"key":16,"text":17,"correct":18},"B","在高度不同的加工面上测量水平度时，可在高的平面垫放垫铁",false,{"key":20,"text":21,"correct":18},"C","对于一些精度要求不高的设备，可以采用光学仪器进行测量",{"key":23,"text":24,"correct":18},"D","对于一些精度要求高和测点距离远的可采用液体连通器和钢板尺进行测量","在高度不同的加工面上测量水平度时，不可在高的平面垫放垫铁，对于一些精度要求高和测点距离远的可不采用液体连通器和钢板尺进行测量。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]