[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1265580,853,1,"单选题","某外资厂房设备安装工程由D公司中标承建。由于设备全部为国外进口机器，精密度要求较高，为了确保安装精准，项目部引进了与项目要求匹配的先进测量工具，并加强测量控制。由于前期工作准备充分，设备在安装定位及抄平过程中未出现问题，经检测完全符合设计要求。根据背景材料，回答以下问题。 项目部在确定基准中心点时，由于该厂房无固定水准点和中心线，则可直接利用（ ）为基准确定基准中心点。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","临时水准点",false,{"key":16,"text":17,"correct":14},"B","厂房柱子",{"key":19,"text":20,"correct":21},"C","设备基础",true,{"key":23,"text":24,"correct":14},"D","沉降观测点","在确定基准中心点时，由于该厂房无固定水准点和中心线，则可直接利用设备基础为基准确定基准中心点。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]