[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1265571,853,1,"单选题","设备标高基准点从建筑物的标高基准点引人到其他设备的基准点时，应一次完成。对一些大型、重型设备，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","多布置一些基准点",true,{"key":16,"text":17,"correct":18},"B","少布置一些基准点",false,{"key":20,"text":21,"correct":18},"C","只布置一个基准点",{"key":23,"text":24,"correct":18},"D","杜绝使用永久基准点","设备标高基准点从建筑物的标高基准点引人到其他设备的基准点时，应一次完成。对一些大型、重型设备，应多布置一些基准点。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]