[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1265502,853,1,"单选题","垂直管道金属保护层的敷设方法和要求是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由下而上施工，接缝应上搭下",true,{"key":16,"text":17,"correct":18},"B","由上而下施工，接缝应上搭下",false,{"key":20,"text":21,"correct":18},"C","由下而上施工，接缝应下搭上",{"key":23,"text":24,"correct":18},"D","由上而下施工，接缝应下搭上","金属保护层施工技术要求中，垂直管道或设备金属保护层的敷设，应由下而上进行施工，接缝应上搭下。金属保护层的接缝可选用搭接、咬接、插接及嵌接的形式。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]