[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265445":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1265445,853,1,"单选题","汽轮机低压外下缸组合程序是在外下缸后段（电机侧）和前段（汽侧）先分别就位，试组合符合要求后，将前、后段分开一段距离，再次清理检查（ ），确认无异物后，再进行正式组合。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水平结合面",false,{"key":16,"text":17,"correct":18},"B","垂直结合面",true,{"key":20,"text":21,"correct":14},"C","纵向结合面",{"key":23,"text":24,"correct":14},"D","横向结合面","低压外下缸组合包括：低压外下缸后段（电机侧）与低压外下缸前段（汽测）先分别就位，调整水平、标高、找中心后试组合，符合要求后，将前、后段分开一段距离，再次清理检查垂直结合面，确认清洁无异物后再进行正式组合。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]