[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1265307,853,1,"单选题","按照变更的内容，设计变更可分为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","重大设计变更、较大设计变更、一般设计变更",false,{"key":16,"text":17,"correct":18},"B","重大设计变更、一般设计变更",true,{"key":20,"text":21,"correct":14},"C","特大设计变更、较大设计变更、一般设计变更",{"key":23,"text":24,"correct":14},"D","较大设计变更、一般设计变更","设计变更按照变更的内容可分为：①重大设计变更，是指变更对项目实施总工期和里程，产生影响，或增加的费用超出批准的基础设计概算，或增加原批准概算中没有列入的单项工程，或工艺方案变化、扩大设计规模、增加设备等改变础设计范围等原因提出的设计变更。②一般设计变更，是指在不违背批准的基础设计文件的前提下，发生的局部改进、完善、使设计更趋于合理、优化，以及更好地满足用户的需求等方面的设计变更。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]