[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265260":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1265260,853,1,"单选题","某安装公司中标了C市一大型写字楼机电安装工程，内容包含室内给水排水、电气照明、配电房、通风与空调系统、消防及智能化监控系统等。项目部在施工过程中严格遵守施工规范及验收标准，利用PDCA循环加强质量控制。项目最终验收合格，顺利投人使用。根据背景材料，回答以下问题。 5月时施工班组完成了室内给水管道的安装，后续工艺流程正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","压力试验→冲洗消毒→防腐绝热→通水验收",false,{"key":16,"text":17,"correct":14},"B","防腐绝热→压力试验→冲洗消毒→通水验收",{"key":19,"text":20,"correct":14},"C","防腐绝热→冲洗消毒→压力试验→通水验收",{"key":22,"text":23,"correct":24},"D","压力试验→防腐绝热→冲洗消毒→通水验收",true,"室内给水管道的安装，后续工艺流程为压力试验→防腐绝热→冲洗消毒→通水验收",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]