[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265256":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1265256,853,3,"判断题","高效空气过滤器应在洁净室（区）建筑装饰装修和配管工程施工已完成并验收合格，洁净室（区）已进行全面清洁、擦净，净化空调系统已进行擦净和连续试运转8h以上才能安装。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"高效空气过滤器应在洁净室（区）建筑装饰装修和配管工程施工已完成并验收合格，洁净室（区）已进行全面清洁、擦净，净化空调系统已进行擦净和连续试运转12h以上才能安装。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装质量)基础知识","建筑工程",0]