[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1265213,853,1,"单选题","临时用电设备在（ ）或设备总容量在（ ）者，应编制临时用电施工组织设计",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5台及5台以上50KW及50KW以上",true,{"key":16,"text":17,"correct":18},"B","4台及4台以上50KW及50KW以上",false,{"key":20,"text":21,"correct":18},"C","5台及5台以上40KW及40KW以上",{"key":23,"text":24,"correct":18},"D","6台及6台以上50KW及50KW以上","临时用电设备在5台及5台以上或设备总容量在50KW及50KW以上者，应编制临时用电施工组织设计。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]