[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1264390":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1264390,851,2,"多选题","施工进度计划根据施工项目划分的粗细程度可分为( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","年进度计划",false,{"key":16,"text":17,"correct":18},"B","控制性施工进度计划",true,{"key":20,"text":21,"correct":14},"C","季进度计划",{"key":23,"text":24,"correct":18},"D","指导性施工进度计划",{"key":26,"text":27,"correct":14},"E","月进度计划","BD","",{"id":6,"name":31,"category":32,"favorite":33},"装饰方向-岗位技能","建筑工程",0]