[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1264388":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1264388,851,2,"多选题","控制性施工进度计划主要适用于( )的工程,同时还适用于虽然工程规模不大、结构不算复杂,但各种资源没有落实,或者由于装饰设计的部位、材料等可能发生变化以及其他各种情况。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","任务具体明确",false,{"key":16,"text":17,"correct":18},"B","结构较复杂",true,{"key":20,"text":21,"correct":18},"C","规模较大",{"key":23,"text":24,"correct":18},"D","工期较长需跨年度施工",{"key":26,"text":27,"correct":14},"E","施工工期不太长","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"装饰方向-岗位技能","建筑工程",0]