[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1264328":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1264328,851,2,"多选题","下列有关施工成本考核的说法中,正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","揭示成本变动规律,寻找降低施工项目成本的途径",false,{"key":16,"text":17,"correct":18},"B","以施工成本降低额和降低率作为成本考核的主要指标",true,{"key":20,"text":21,"correct":18},"C","可分别考核组织管理层和项目经理部",{"key":23,"text":24,"correct":18},"D","是对成本指标完成情况的总结和评价",{"key":26,"text":27,"correct":18},"E","是实现成本目标责任制的保证","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"装饰方向-岗位技能","建筑工程",0]