[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1264174":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1264174,851,1,"单选题","施工进度计划根据施工项目划分的粗细程度可分为( ):",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","年进度计划和实实性进度计划",false,{"key":16,"text":17,"correct":14},"B","控制性施工进度计划和实施性进度计划",{"key":19,"text":20,"correct":14},"C","季进度计划和实施性进度计划",{"key":22,"text":23,"correct":24},"D","指导性施工进度计划和控制性施工进度计划",true,"",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]