[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1264153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1264153,851,1,"单选题","施工成本计划应满足的要求不包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以经济合理的项目实施方案为基础的要求",false,{"key":16,"text":17,"correct":14},"B","合同规定的项目质量和工期要求",{"key":19,"text":20,"correct":21},"C","控制影响效率的其他因素的要求",true,{"key":23,"text":24,"correct":14},"D","有关定额及市场价格的要求","",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]