[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1264149":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1264149,851,1,"单选题","在项目的实施过程中,需按( )对实际施工成本的发生过程进行有效控制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","动态控制原理",true,{"key":16,"text":17,"correct":18},"B","静态控制原理",false,{"key":20,"text":21,"correct":18},"C","宏观控制原理",{"key":23,"text":24,"correct":18},"D","微观控制原理","",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]