[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1264148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1264148,851,1,"单选题","施工成本控制的工作内容之一是计算和分析( )之间的差异。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预测成本与实际成本",false,{"key":16,"text":17,"correct":14},"B","预算成本与计划成本",{"key":19,"text":20,"correct":21},"C","计划成本与实际成本",true,{"key":23,"text":24,"correct":14},"D","预算成本与实际成本","",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]