[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1264139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1264139,851,1,"单选题","某项目进行成本偏差分析,结果为:已完工作预算成本(BCWP)已完工作实际成本(ACWP)＜0;已完工作预算成本(BCWP)一计划完成工作预算成本(BCWS》＞0。则说明( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本超支,进度提前",true,{"key":16,"text":17,"correct":18},"B","成本节约,进度提前",false,{"key":20,"text":21,"correct":18},"C","成本超支,进度拖后",{"key":23,"text":24,"correct":18},"D","成本节约,进度拖后","",{"id":6,"name":27,"category":28,"favorite":29},"装饰方向-岗位技能","建筑工程",0]