[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-175518":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},175518,85,2,"多选题","下列关于投资回收期的说法，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投资回收期反映了项目的财务投资回收能力",true,{"key":16,"text":17,"correct":18},"B","投资回收期是项目的累计净现金流量开始出现正值的年份数",false,{"key":20,"text":21,"correct":18},"C","投资回收期应是整数",{"key":23,"text":24,"correct":18},"D","项目投资回收期大于行业基准回收期，表明该项目能在规定的时间内收回投资",{"key":26,"text":27,"correct":14},"E","投资回收期是用项目净收益抵偿项目全部投资所需的时间","AE","投资回收期是指用项目净收益抵偿项目全部投资所需的时间，它是项目在财务投资回收能力方面的主要评价指标。投资回收期=累计净现金流量开始出现正值的年份数-1+上年累计净现金流量绝对值\u002F当年净现金流量，并未规定一定要是整数。当项目投资回收期小于或等于行业基准回收期时，表明该项目能在规定的时间内收回投资。",{"id":6,"name":31,"category":32,"favorite":33},"公司信贷","经济金融",0]