[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-173396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},173396,85,1,"单选题","水力发电站规模主要根据水源流量和落差来确定，这里的水源流量和落差属于()项目规模制约因素。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","行业技术经济特点",true,{"key":16,"text":17,"correct":18},"B","环境",false,{"key":20,"text":21,"correct":18},"C","设备、设施状况",{"key":23,"text":24,"correct":18},"D","其他生产建设条件","由于不同的项目所处行业的技术经济特点不同，因此不同的部门和行业对项目生产规模有不同的要求。水力发电站根据水源流量和落差确定建设规模，主要是基于行业技术经济特点对生产规模的要求和限制的考虑。",{"id":6,"name":27,"category":28,"favorite":29},"公司信贷","经济金融",0]