[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-173374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},173374,85,1,"单选题","下列不属于项目建设必要性评估的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目所属行业目前整体状况",false,{"key":16,"text":17,"correct":14},"B","项目产品所处生命周期",{"key":19,"text":20,"correct":14},"C","项目产品的市场情况",{"key":22,"text":23,"correct":24},"D","项目的盈利能力与清偿能力",true,"项目建设必要性评估主要是对项目所属行业目前整体情况、项目产品所处生命周期、项目产品市场情况及产品竞争力三方面进行的评估。D项属于财务评估的内容。",{"id":6,"name":27,"category":28,"favorite":29},"公司信贷","经济金融",0]