[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-173316":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},173316,85,1,"单选题","银行在对项目进行技术及工艺流程分析时，以下做法不正确的是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","产品技术方案分析无须考虑市场的需求状况",true,{"key":16,"text":17,"correct":18},"B","分析产品的质量标准时，应将选定的标准与国家标准、国际常用标准进行对比",false,{"key":20,"text":21,"correct":18},"C","对生产工艺进行评估，首先要熟悉项目产品国内外有关资料，分析各方法的优缺点",{"key":23,"text":24,"correct":18},"D","分析工艺技术方案的选择是否与社会发展目标相符合","产品技术方案分析，就是分析项目产品的规格、品种、技术性能以及产品的质量。产品技术方案分析一方面要分析产品方案和市场需求状况，另一方面要分析拟建项目的主要产品和副产品所采用的质量标准是否符合要求。所以A选项错误。",{"id":6,"name":27,"category":28,"favorite":29},"公司信贷","经济金融",0]