[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-172826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},172826,85,1,"单选题","商业银行对于投资额大、技术复杂、按照项目进度分期付款的固定资产贷款项目，在借款人提取贷款时，一般应要求借款人提供（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","银团贷款代理行签署确认的项目进度和质量的书面文件",false,{"key":16,"text":17,"correct":18},"B","有监理、评估、质检等第三方机构参与签署的确认项目进度和质量的书面文件",true,{"key":20,"text":21,"correct":14},"C","施工单位签署确认的项目进度和质量的书面文件",{"key":23,"text":24,"correct":14},"D","当地政府签署确认的项目进度和质量的书面文件","对于投资额大、技术复杂、按照项目进度分期付款的固定资产投资项目，贷款人一般要求借款人提供有监理、评估、质检等第三方机构参与签署的确认项目进度和质量的书面文件，包括但不限于借款人、承包商以及第三方机构共同签署的单据等。",{"id":6,"name":27,"category":28,"favorite":29},"公司信贷","经济金融",0]