[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263895":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1263895,849,3,"判断题","基础工程施工阶段的施工顺序一般是:挖土方→垫层→基础→回填土。具体内容视工程设计而定。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"",{"id":6,"name":21,"category":22,"favorite":23},"土建方向-岗位技能","建筑工程",0]