[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263841":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263841,849,2,"多选题","施工进度计划的编制依据主要包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目可行性研究报告",false,{"key":16,"text":17,"correct":18},"B","经过审批的全套施工图及各种采用的标准图和技术资料",true,{"key":20,"text":21,"correct":18},"C","工程的工期要求及开工、竣工日期",{"key":23,"text":24,"correct":18},"D","工程项目工作顺序及相互间的逻辑关系",{"key":26,"text":27,"correct":18},"E","项目工作的提前和滞后要求","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"土建方向-岗位技能","建筑工程",0]