[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263839":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263839,849,2,"多选题","下列说法正确的是( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","总时差为最小的工作为关键工作",true,{"key":16,"text":17,"correct":14},"B","自始至终全部由关键工作组成的线路为关键线路",{"key":19,"text":20,"correct":14},"C","线路上总的工作持续时间最长的线路为关键线路",{"key":22,"text":23,"correct":24},"D","自由时差为最小的工作为关键工作",false,{"key":26,"text":27,"correct":24},"E","时标网络计划中波形线水平投影长度为总时差","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"土建方向-岗位技能","建筑工程",0]