[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263794":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263794,849,2,"多选题","施工进度计划编制依据包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","约束条件",true,{"key":16,"text":17,"correct":14},"B","工程的工期要求及开工、竣工日期",{"key":19,"text":20,"correct":14},"C","资源需求",{"key":22,"text":23,"correct":24},"D","施工方法",false,{"key":26,"text":27,"correct":14},"E","作业制度安排","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"土建方向-岗位技能","建筑工程",0]