[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263793":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1263793,849,2,"多选题","施工进度计划的审核内容包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","进度安排是否符合施工合同确定的建设项目总目标和分目标的要求",true,{"key":16,"text":17,"correct":14},"B","施工进度计划中的内容是否有遗漏,分期施工是否满足分批交工的需要和配套交工的要求",{"key":19,"text":20,"correct":14},"C","施工顺序安排是否符合施工程序的要求",{"key":22,"text":23,"correct":14},"D","资源供应计划是否能保证施工进度计划的实现,供应是否均衡,分包人供应的资源是否满足进度要求",{"key":25,"text":26,"correct":14},"E","施工图设计的进度是否满足施工进度计划要求","ABCDE","",{"id":6,"name":30,"category":31,"favorite":32},"土建方向-岗位技能","建筑工程",0]