[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263788":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263788,849,2,"多选题","编制建设工程施工总进度计划,主要用来确定如下哪几项工作( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","各单项工程或单位工程的工期定额",false,{"key":16,"text":17,"correct":14},"B","建设的要求工期和计算工期",{"key":19,"text":20,"correct":21},"C","各单项工程或工程的施工期限",true,{"key":23,"text":24,"correct":14},"D","各单项工程或单位工程的实物工程量",{"key":26,"text":27,"correct":21},"E","各单项工程或单位工程的相互搭接关系","CE","",{"id":6,"name":31,"category":32,"favorite":33},"土建方向-岗位技能","建筑工程",0]