[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263786":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263786,849,2,"多选题","在施工进度计划的调整过程中,压缩关键工作持续时间的技术措施有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加劳动力和施工机械的数量",false,{"key":16,"text":17,"correct":18},"B","改进施工工艺和施工技术",true,{"key":20,"text":21,"correct":18},"C","采用更先进的施工机械",{"key":23,"text":24,"correct":14},"D","改善外部配合条件",{"key":26,"text":27,"correct":14},"E","采用工程分包方式","BC","",{"id":6,"name":31,"category":32,"favorite":33},"土建方向-岗位技能","建筑工程",0]