[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263785":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1263785,849,2,"多选题","当实际施工进度发生拖延时,为加快施工进度而采取的组织措施可以是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加工作面和每天的施工时间",true,{"key":16,"text":17,"correct":18},"B","改善劳动条件并实施强有力的调度",false,{"key":20,"text":21,"correct":18},"C","采用更先进的施工机械和施工方法",{"key":23,"text":24,"correct":18},"D","改进施工方法,减少施工过程的数量",{"key":26,"text":27,"correct":14},"E","增加劳动力和施工机械的数量","AE","",{"id":6,"name":31,"category":32,"favorite":33},"土建方向-岗位技能","建筑工程",0]