[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1263702,849,1,"单选题","施工进度计划在编制时,工程量计算应注意很多事项,其中不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","划分的施工段数",true,{"key":16,"text":17,"correct":18},"B","工程量的计量单位",false,{"key":20,"text":21,"correct":18},"C","采用的施工方法",{"key":23,"text":24,"correct":18},"D","正确取用计价文件中的工程量","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]