[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263695":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1263695,849,1,"单选题","组织流水施工时,空间参数不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工层数",false,{"key":16,"text":17,"correct":18},"B","流水步距",true,{"key":20,"text":21,"correct":14},"C","工作面",{"key":23,"text":24,"correct":14},"D","施工段数","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]