[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263694":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1263694,849,1,"单选题","组织流水施工时,时间参数不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","流水节拍",false,{"key":16,"text":17,"correct":14},"B","流水步距",{"key":19,"text":20,"correct":14},"C","工期",{"key":22,"text":23,"correct":24},"D","施工段",true,"",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]