[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1263631,849,1,"单选题","确定施工顺序的基本要求不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","必须符合施工工艺的要求",false,{"key":16,"text":17,"correct":14},"B","必须与施工方法协调一致",{"key":19,"text":20,"correct":14},"C","必须考虑当地的气候条件",{"key":22,"text":23,"correct":24},"D","必须考虑文明施工的要求",true,"",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]