[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263627":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1263627,849,1,"单选题","施工进度计划的审核内容不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度安排是否符合上级规定",true,{"key":16,"text":17,"correct":18},"B","施工进度计划中的内容是否有遗漏,分期施工是否满足分批交工的需要和配套交工的要求",false,{"key":20,"text":21,"correct":18},"C","施工顺序安排是否符合施工程序的要求",{"key":23,"text":24,"correct":18},"D","资源供应计划是否能保证施工进度计划的实现,供应是否均衡,分包人供应的资源是否满足进度要求","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]