[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1263619,849,1,"单选题","下列不属于施工进度计划的调整方法的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","加强安全教育",true,{"key":16,"text":17,"correct":18},"B","增加资源投入",false,{"key":20,"text":21,"correct":18},"C","增减工作范围",{"key":23,"text":24,"correct":18},"D","提高劳动效率","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]