[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1263618,849,1,"单选题","在工程网络计划中,下列关于关键线路的说法错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","双代号网络计划中总持续时间最长",false,{"key":16,"text":17,"correct":14},"B","相邻的两项工作之间时间间隔均为零",{"key":19,"text":20,"correct":21},"C","单代号网络计划中由关键工作组成",true,{"key":23,"text":24,"correct":14},"D","时标网络计划中自始至终无波形线","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]