[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1263617,849,1,"单选题","施工作业计划分月施工作业计划和旬（周）施工作业计划。下列选项中不属于其内容的为( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","本月、旬（周）应完成的施工任务",false,{"key":16,"text":17,"correct":14},"B","完成作业计划任务所需的劳力、材料、半成品、构配件等的需用量",{"key":19,"text":20,"correct":14},"C","提高劳动生产率的措施和节约措施",{"key":22,"text":23,"correct":24},"D","质量计划",true,"",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]