[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1263607,849,1,"单选题","某工程项目桩基工程采用套管成孔灌注桩,为了保证施工质量,桩管灌满混凝土后开始拔管,按照规定,管内应保持不少于( )m高的混凝土。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","1.5",{"key":19,"text":20,"correct":21},"C","2",true,{"key":23,"text":24,"correct":14},"D","2.5","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]