[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1263601,849,1,"单选题","某公司承接一公寓工程,则该工程的施工进度计划应由( )编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工承包企业",true,{"key":16,"text":17,"correct":18},"B","建设单位",false,{"key":20,"text":21,"correct":18},"C","监理单位",{"key":23,"text":24,"correct":18},"D","项目经理","",{"id":6,"name":27,"category":28,"favorite":29},"土建方向-岗位技能","建筑工程",0]