[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1263386,848,1,"单选题","真空预压的施工顺序一般为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设置竖向排水体→铺设排水垫层→埋设滤管→开挖边沟→铺膜、填沟、安装射流泵等→抽空→抽真空、预压",false,{"key":16,"text":17,"correct":14},"B","铺设排水垫层-设置竖向排水体→开挖边沟-埋设滤管→铺膜、填沟、安装射流泵等→抽空→抽真空、预压",{"key":19,"text":20,"correct":21},"C","铺设排水垫层→设置竖向排水体→埋设滤管→开挖边沟→铺膜、填沟、安装射流泵等→抽空→抽真空、预压",true,{"key":23,"text":24,"correct":14},"D","铺设排水垫层→设置竖向排水体→埋设滤管→开挖边沟→抽空→铺膜、填沟、安装射流泵等→抽真空、预压","",{"id":6,"name":27,"category":28,"favorite":7},"市政方向-通用基础","建筑工程"]