[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1263382":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1263382,848,1,"单选题","水泥粉煤灰碎石桩的施工工艺流程为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","桩位测量-桩机就位→钻进成孔→混凝土浇筑→移机→检测→褥垫层施工",true,{"key":16,"text":17,"correct":18},"B","桩机就位→桩位测量→钻进成孔→混凝土浇筑→移机→检测→褥垫层施工",false,{"key":20,"text":21,"correct":18},"C","桩位测量→桩机就位→钻进成孔→移机→混凝土浇筑→检测→褥垫层施工",{"key":23,"text":24,"correct":18},"D","桩机就位→桩位测量→钻进成孔→移机→混凝土浇筑→检测_褥垫层施工","",{"id":6,"name":27,"category":28,"favorite":7},"市政方向-通用基础","建筑工程"]